Temporary forces during the bridge construction phase due to the deadweight of equipment are called which load?

Discover the essentials of bridge engineering. Study with interactive quizzes, detailed questions, hints, and explanations. Prepare effectively for your test with engaging content and insight into exam expectations and formats. Achieve success on your exam today!

Multiple Choice

Temporary forces during the bridge construction phase due to the deadweight of equipment are called which load?

Explanation:
During construction, there are loads that are temporary and tied to the erection activities themselves. The deadweight of equipment, forms, scaffolding, and other temporary works is captured under construction load because it exists only during the building process and is not a part of the finished structure. This contrasts with dead load, which is the permanent weight of the completed bridge; live load, which comes from use and occupancy; wind load, which is an environmental force; and design lane load, which isn’t a standard term for construction-stage effects. So, the temporary forces from construction equipment are categorized as construction load.

During construction, there are loads that are temporary and tied to the erection activities themselves. The deadweight of equipment, forms, scaffolding, and other temporary works is captured under construction load because it exists only during the building process and is not a part of the finished structure. This contrasts with dead load, which is the permanent weight of the completed bridge; live load, which comes from use and occupancy; wind load, which is an environmental force; and design lane load, which isn’t a standard term for construction-stage effects. So, the temporary forces from construction equipment are categorized as construction load.